Commercial and industrial boilers are not replaced often (once every 15-50 years, depending on the size of the boiler). Because most facility managers responsible for HVAC systems don’t tackle this project regularly, they usually engage third-party engineers to help facilitate the process. This happened for one of our healthcare clients in Connecticut.
Our mechanical team is currently hard at work on a large boiler retrofit project for the hospital. Their existing boilers were 49 years old and a replacement will provide immense energy savings and significant operational benefits for this hospital. The following three steps outline the basic project process most commercial/industrial businesses can expect when taking on a boiler retrofit.
We should acknowledge that a boiler replacement project is a large and complicated task. While these three steps offer a framework, all major HVAC projects should be handled by experienced teams, engineering staff and professionals in the field.
There are a lot of considerations to account for in the engineering and design phase of a boiler replacement project. These can include emissions permitting, proper sizing of new boilers, fuel options, boiler type, controls, physical space constraints/restrictions, future requirements, potential utility incentives, budget and schedule. Many of these issues are conflicting and a design must be developed that optimizes the issues. The challenges that came into play for this Connecticut hospital example project included the following:
The final design incorporated all of the design requirements above to meet facility demands and the hospital staff’s expectations.
Installation of two 20,000 lb/Hr firetube boilers with economizers and a highly sophisticated burner equipped with O2 trim. The boilers are duel fuel capable of burning either natural gas or No. 2 oil. A No. 2 oil tank and pumping system was also included. Due to the size of the boilers and the combustion equipment selected, the emissions were below the threshold requiring extensive modeling.
The selected boiler sizes would allow one boiler to be out of commission and still have sufficient boiler capacity to satisfy the heating requirement. The high efficiency of the chosen boilers qualified for $500,000 of utility incentives. Finally, the boilers and systems could be installed with construction starting in the spring and boilers operational before the next winter heating season.
Once the equipment is finalized and on order, the construction phase must be planned and executed. Primary steps include:
At a Connecticut hospital project, the boiler room doorway had to be enlarged to allow access for the new boilers.
After the boilers are installed and connected electrically and mechanically there are several steps of startup and commissioning that must be executed.
These steps include:
Our mechanical team will work with a variety of partners to execute the final preparation before start-up and educate the onsite facilities staff to get them ready for their new system.
All boiler installations, like all energy projects in general, are unique to the specific facility we’re working in. We don’t always have to enlarge the doorway for every boiler installation. However, most of the above steps still apply to most commercial or industrial boiler. Prior to any replacement, we’ll always finalize engineering and design, plan and execute the construction and perform boiler startup and commissioning.
Ultimately, planning ahead is the key to any successful energy efficiency installation (and one of the key benefits of working with an ESCO). This post helps to illustrate all the considerations that go into an installation, the planning that needs to occur ahead of time and the attention to detail required to best execute a major energy retrofit or replacement project.